In this project first, 10-ton tanks were installed, and in the next step, a blender was built to mix milk with dry ingredients. Since the milk must be heated at this stage and after mixing completely, it should be transferred to the pasteurizer with the help of a milk pump. Therefore, a fully automatic pasteurizer with Alfa Laval brand pneumatic valves was also equipped. It should be noted that Siemens brand and SCADA WinCC have been used to implement PLCs.

1. Employer

Pajan Dairy Company

4. Production Capacity

5 tons per hour

2. Implementation Time

6 months

5. Implementation Cases

Installation and Industrial Automation

3. Year

2018

6. Country

Tehran, Iran

Project Images

پروسس بستنی 1
پروسس بستنی 2
پروسس بستنی 3

NeedHelp?

Free Consultation

"*" indicates required fields

1

Counseling

Providing expert advice by the technical team

2

Experienced Engineers

Taking advantage of the experiences of experienced engineers

3

Warranty

Warranty and after-sales service for 1 year

Back to list

Related projects